Projects Update

Banjul Port Project II - Utilisation of Savings

Re-Design and Extension of Computer Network Cabling

Construction of A Car Terminal


Banjul Port Project II - Utilisation of Savings  

This project comprises of  components B, D and E.

Component B - Rehabilitation of Old Banjul Wharf

This components entails the rehabilitation of the Old Banjul Wharf constructed in the early 70s by Balfore Betty, Civil Engineering Contractors.  The works consists of concrete repairs, fenders replacement, upgrading of Fire-fighting system, etc.

Other than adequately addressing the maintenance requirements of the Jetty, the objectives of this project include safeguarding the international competitiveness of the Port of Banjul by providing adequate facilities for the efficient handling of cargoes to avoid deterioration of services to ships as the growing traffic pushes the berth occupancy rate above optimal levels.

The execution of the project is in progress.

Component D - Update of the 1992 Feasibility Study and Masterplan 

The purpose of the consulting services is to provide the Government of the Gambia and the GPA with an update of the Authority's Masterplan including recommendations for the provision of facilities and services aimed at maximizing on the core competence of the Port while addressing the challenges that lie ahead.

Approval from the Bank is awaited to sign the contract with Hamburg Port Consulting of Germany.

 Component D - Project Audit

The objective of the audit is to enable the auditor to express his professional opinion on the financial position of the Banjul Port Project II, loan No. F/GAM/Por-2/94/ and of the resources and expenditures for the accounting period ended 31st December 2000 and at six monthly intervals thereon until the completion of the project.

The final approval has been obtained from the ADB, requesting the GPA to proceed with negotiations with the successful tender, Deloitte & Touche.

Component E - Procurement of Cargo Handling Equipment

In its endeavor to keep abreast with increasing cargo throughput, the GPA embarks on the procurement of Cargo Handling Equipment in order to :-

-Improve and enhance the Port's operation and throughput capacity

-Provide additional capacity to meet present and future traffic demand

-To render ship waiting time to avoid congestion surcharges and demurrages

-Attract new shipping lines such as gear -less ship and RO-RO vessel.

 

UKRAINE PROJECT

The Gambia Ports Authority (GPA) on behalf of the Government of The Gambia has entered into a contract with Kiev Shipbuilding AND ship Repair Yard of Ukraine (KSSRY), for the construction and delivery of two car/passenger ferries and one floating dock. The contract is expected to be signed on the 14th February 2002 and will be implemented over the period of thirty calendar months (inclusive of the 1 year warranty period for each of the crafts). The crafts are to be delivered to The Gambia within 16-19 months after the effectiveness of the contact (19th April, 2002).

The three floating crafts will be deployed as follows:

i) One car/passenger ferry for Banjul/Barra

ii) One car/passenger ferry for Transgambia

iii) one floating dock for Banjul Shipyard

The building/construction of the above crafts shall take place at the Kiev Shipbuilding and Ship Repair Yard in Ukraine.

The total contract price is US$7,090,000.00 (United States Dollars, Seven million and ninety thousand only). This amount is financed by a loan agreement between Standard Charted Bank (G) Ltd and the Gambia Ports Authority.

Back To The Top

Re-Design and Extension of Computer Network Cabling

As a result of rapid extensions of  the Authority's computer network and the short-comings of the Bus Network Topology then in existence, the GPA in May 2000 embarked on a project to re-design and extension of the network to the more efficient Smart Star Hub Topology to include the Document Handling Centre, Sheds, Stevedores and Clinic areas which came up to a total of over 100 points.

The Project was tendered and the contract awarded to Quantum Associates Ltd.  Work has since commenced at the Head Office, Stores and Workshop areas have been completed.  The others areas are expected to be operational in August 2001.

Additional computers are also being procured to replace old and PCs and for use in the new extensions.

The project is also expected to lay the foundation for the upcoming full Port Computerisation project which will be funded by the African Development Bank.

Back To The Top

Car Terminal

It came to the attention of Management that the Lorry Waiting Area that had been constructed under the Third Banjul Port Project - Component A is presently not being put to its designed purpose. There is also an adjacent strip of land, lying west of the said Lorry Waiting Area but located within the Bonded Warehouses Complex, that is not paved and is not being utilised.

Newly improved vehicles, waiting to be collected by their owners, are being parked at the former location of demolished Transit Sheds B&C thereby taking up space that could be put to a more profitable use. This is clearly not in line with Management's policy of exploiting every opportunity to improve upon the profitability of the Port.

It is against this background that the idea of converting the above-mentioned spaces into a carport was conceived. In this way, much needed space would be created at the terminals closest to the jetties and the under utilized areas in question put to more profitable use.

This payment has recently been completed.

Back To The Top

 

[Home] [About Us] [Our Advantages] [Operations] [Vessel Movements]

[IT Systems] [HR] [Port Community] [Inter-port Co-operation] [Contact Us]

Send mail to the Web Administrator with questions or comments about this web site
Copyright © 2000 Gambia Ports Authority
Last modified: January 21, 2003